«maintenance (TO-15000) of gas-piston
power plants...»
The maintenance project (TO-15000) for two
Zvezda GP 1100 VK-02M3-120 gas-piston power plants included
a set of maintenance and repair activities.
December 2020 / «Gazprom Dobycha Kuznetsk LLC»
«major repairs of internal combustion engines...»
SOYUZ Control Center LLC (now RODVIG) performed with special responsibility, in strict accordance with the documentation, major repairs and replacement of Equipment, Cummins QSK-60G8 and Cummins KTA-50G3 internal combustion engines, as well as pre-capital repairs and replacement of internal combustion engines at the facilities of RUSVIETPETRO IC LLC.
November 2020 / RUSVIETPETRO IC LLC
«large-scale overhaul of the Cummins
QSV 91-GS60000 GPS...»
In 2021, our company carried out a large-scale overhaul of the Cummins QSV 91-G TO-60000 GPP, ongoing repairs of the Cummins QSV 91-G GPP, calibration of the GPP based on Cummins QSV 91-G engines, ongoing repairs of the Cummins KTA-50G3 6000 GPP.
November 2021 / RUSVIETPETRO IC LLC
«major repairs of the gas piston power plant (GPP)...»
Our company has carried out major repairs of the Cummins QSV 91-G gas piston power plant (GPP) at the Energy Center No. 1 of the Severo-Khosedayu oil field named after A. Slivka in the amount of TO-60,000.
This overhaul involves a comprehensive restoration and renovation of the power plant using RODVIG spare parts and compliance with all technical requirements.
May 2022 / RUSVIETPETRO IC LLC
«calibration of the gas-air mixture...»
RODVIG specialists calibrated the gas-air mixture at the facilities of GPU No. 1, GPU No. 2, GPU No. 3, GPU No. 4, GPU No. 5, GPU No. 6, GPU No. 7 and GPU No. 8.
Calibration of the gas-air mixture is an important stage in the maintenance of gas processing equipment, which makes it possible to optimize the operation of installations, increase process efficiency and ensure operational safety.
March 2024 / Salekhardenergo JSC
«maintenance (TO-60000) of a gas piston power plant...»
In October 2024, RODVIG specialists successfully completed
the maintenance (TO-60000) of a gas piston power plant
in the village Aksarka.
October 2024 / Harp-Energo-Gaz JSC